A Installing the casing pipe B Attaching the reamer C Drilling the pilot hole D Widening the pilot hole E The purpose of HDD F Stages in the HDD process G Main components H Function of components Horizontal Directional Drilling (HDD) 33 _____ Horizontal Directional Digging is used by the oil and gas industry for installing casing pipes under rivers or other obstacles. 34 _____ The equipment consists of a portable rig, a drill string, a cutter, a reamer, and a casing pipe. 35 _____ The job of the portable rig is to provide power for the drilling operation. The rig is attached to the drill string, the cutter and the reamer. The drill string transmits a rotating movement to the cutter. The purpose of the cutter is to make the pilot hole. The function of the reamer is to widen the small hole to the correct diameter. 36 _____ There are four main steps involved in horizontal directional digging. Let’s look at these four steps one by one. 37 _____ First, a small pilot hole is made using the drill bit on the end of the drill string. The drill bit completes the pilot hole and exits from the other side. 38 _____ Next, the cutter is removed from the drill string and the reamer is fixed to it. 39 _____ The drill string with the reamer attached is then pulled back through the pilot hole. As the reamer moves backwards through the hole, it increases the diameter of the hole. 40 _____ Finally, the drill string pulls the casing pipe through the hole, and the tunnel is completed.

Lời giải 1 :

33 _____Horizontal Directional Drilling (HDD)
Horizontal Directional Digging is used by the oil and gas industry for installing casing pipes under rivers or other obstacles.  ( giới thiệu ) 
34 _____G Main components
The equipment consists of a portable rig, a drill string, a cutter, a reamer, and a casing pipe.
35 _____E The purpose of HDD
The job of the portable rig is to provide power for the drilling operation. The rig is attached to the drill string, the cutter and the reamer. The drill string transmits a rotating movement to the cutter. The purpose of the cutter is to make the pilot hole. The function of the reamer is to widen the small hole to the correct diameter.
36 _____F Stages in the HDD process
There are four main steps involved in horizontal directional digging. Let’s look at these four steps one by one.
37 _____C Drilling the pilot hole
First, a small pilot hole is made using the drill bit on the end of the drill string. The drill bit completes the pilot hole and exits from the other side.
38 _____B Attaching the reamer
Next, the cutter is removed from the drill string and the reamer is fixed to it.
39 _____D Widening the pilot hole
The drill string with the reamer attached is then pulled back through the pilot hole. As the reamer moves backwards through the hole, it increases the diameter of the hole.
40 _____A Installing the casing pipe
Finally, the drill string pulls the casing pipe through the hole, and the tunnel is completed.

Thảo luận

Bạn có biết?

Tiếng Anh hay Anh Ngữ (English /ˈɪŋɡlɪʃ/ ) là một ngôn ngữ German Tây, được nói từ thời thời Trung cổ tại Anh, ngày nay là lingua franca toàn cầu.Từ English bắt nguồn từ Angle, một trong những bộ tộc German đã di cư đến Anh (chính từ "Angle" lại bắt nguồn từ bán đảo Anglia (Angeln) bên biển Balt)

Nguồn : Wikipedia - Bách khoa toàn thư

Tâm sự 10

Lớp 10 - Năm thứ nhất ở cấp trung học phổ thông, năm đầu tiên nên có nhiều bạn bè mới đến từ những nơi xa hơn vì ngôi trường mới lại mỗi lúc lại xa nhà mình hơn. Được biết bên ngoài kia là một thế giới mới to và nhiều điều thú vị, một trang mới đang chò đợi chúng ta.

Nguồn : ADMIN :))

Liên hệ hợp tác hoặc quảng cáo: gmail

Điều khoản dịch vụ

Copyright © 2021 HOCTAPSGK